Copper wire and the rewire bill

Desk note. Data through October 2026.

The producer price index for copper wire and cable reached 610.0 in October 2026, a record. It is up 25.5% in twelve months, up 51.8% in five years and up 142.6% in ten. No other series on this site leads on all three spans.

501001502002502010201520202025205.3154.3139.2Copper wire and cableMaterials compositeElectrical contractors, hourly pay
Copper wire and cable, the materials composite and electricians' hourly pay, 2019 = 100. The BLS file has no copper wire value for July 2020. Sources: BLS PPI and CES.

Where it lands in a house

Copper wire is unusual among renovation materials in that the quantity is set by geometry. A panel upgrade needs a fixed length of service cable. A circuit for a car charger, a range or a heat pump needs heavy cable from the panel to the appliance, and the homeowner cannot substitute a cheaper grade. When the index doubles against 2019, as it has (+105.3%), that part of the quote doubles with it.

For most interior remodels the exposure is small. A kitchen adds a few circuits of light-gauge cable and the electrician's time is the larger cost. The jobs to watch are whole-house rewires, service upgrades and long heavy runs.

Labor is rising too

Electrical contractors paid production workers an average of $42.69 an hour in September 2026, up 5.7% on the year, and employed 1.17 million people, up 4.4%. Much of that demand is commercial and industrial. Residential customers are bidding for the same electricians.

Since the end of 2019
SeriesSince Dec 201912 mo1 mo
Copper wire and cable, PPI+105.9%+25.5%+0.6%
Electrical contractors, hourly pay+37.8%+5.7%+0.0%
Electrical contractors, jobs+19.1%+4.4%+0.5%
Materials composite+54.4%+7.7%+0.0%

Reading the index with care

BLS item 10260314 covers copper wire and cable broadly, alongside separate lines for power, telecommunication and electronic cable. It is wider than residential building wire. It also follows the metal, which trades on world markets and can move for reasons unrelated to American housing. The practical consequence is that electrical quotes with a large cable component come with short validity, and a contractor who will not hold a number for sixty days is not being difficult.

Keep reading

Sources

Files retrieved November 2026. The agency files are the authority; where a figure here differs from theirs, theirs is right.